Better Homes and Gardens ®
http://www.bhg.com.au
Cubby house
Your kids will love this
sturdy playhouse
into the ground to mark
position of posts (see diagram). The four
cubby posts (A1) form a square, two
verandah posts (A2) support opposite
verandah corners and one swing post
(A3) holds up the other verandah corner.
Check that set out is square. Dig 500mm
deep holes for the posts. If holes are
deeper than 500mm, add 300mm to post
dimensions. To avoid bracing separate
swing post, set it 1000mm into ground.
Temporarily brace all posts vertically.
floor height on one post.
Use a water level to transfer the mark
to the other posts. Number each post,
remove, then measure 140mm down
from mark. Cut 45mm deep housing
at each of these points, put posts
back in their respective holes, align
the housings and brace them vertically.
Add a bag of concrete mix (two for the
separate swing post) to each hole to
set them in place. Leave overnight.
childhood used to be scrounging
a few offcuts of wood and other bits and
pieces to build a cubby, these days it is
not so easy. Here’s a terrific cubby on
poles, complete with swing and slide,
which will delight the smaller members
of your family and give them a place of
their own.
Continued
Step 1 Drive a number of pegs
Step 2 Mark the 1000mm
W hile one of the greatest joys of
108303517.030.png 108303517.031.png
(B) into housings across
back of cubby, then add two verandah
beams (C) into housings either side of
the verandah. Check for level, then bolt
enclosing beams (D, E, F) to face of
posts so that perimeter is enclosed by
beams. Secure end of cross beam (E)
to verandah beam with three bridge
spikes. Finally add remaining cubby and
verandah beams (B, C) equally spaced
inside the framework using joist hangers.
around posts. Depending on spacing,
one or two may need ripping down to suit
width. Nail in place.
small gap at top. Overlap
sheets; position slightly up from roof
frame ends so they will be covered by
fascias. Add capping (S). Nail fascia
boards (U) to ends of roof frame, then
cut 22.5° angles on barge boards (T).
studs (I). On front wall with
door and window set centre stud to leave
a 640mm space for window frame. Nail
together window frame (J, K) and nail
into wall frame 400mm from top of frame.
Finish wall frame with door head (L)
located 300mm from the top of frame. On
the slippery dip wall also leave a 575mm
opening and install a door head 400mm
from top of frame. Install all the frames
between posts of cubby section, flush
with inside edge. Cut off any projecting
post sections.
finish 800mm above
deck. Add railing by cutting top, bottom
and side channels (V) before fitting
lattice (W). Space bottom channel
125mm from deck, using block offcuts.
Drill 10mm drainage holes in channel.
timber offcuts as nailing
blocks where decking butts against
posts. Cut decking (G) to fit framing and
Step 11 Make a ladder by
screwing rungs (X1)
spaced 250mm apart to rails (X2).
Screw to decking if desired.
Large handles make it
easy for kids to climb
onto the verandah.
Step 6 Cut the top chords (M)
of the roof trusses with a
22.5° angle at each end. Nail together
at the top and lay the assembly over
the bottom chord (N), which has a
final length of 1510mm. The top chord
overhangs are equal. It helps to place a
block under the top joint. Mark the acute
cutting angles on the bottom chord and
cut. Nail together, then add a king post
(O) to support the ridge. Reinforce the
joints with nail plates, then skew-nail to
top of wall frames.
Step 12 Cut swing posts to
2.4m to fit swing beam
(Y), house ends into posts and secure
with long screws and nail plates.
Drill through and fix purpose made
anchors for swing ropes and the
climbing rope to clear by 400mm.
Step 13 Use decking or similar
Step 7 Prepare and nail the roof
door, holding in place
by screwing from underside of cubby.
Clear all obstructions around swing and
slippery dip and provide a soft landing
area. Add a few handles near slippery
dip and ladder. Round and sand all sharp
edges.
(Q) to suit the various wall
panels. Save offcuts to fit around window
and door openings.
WHAT YOU WILL NEED
Item Part Size Material
A1 Cubby posts (4) 90 x 90 x 3000mm Treated pine
A2 Verandah posts (2) 90 x 90 x 2400mm Treated pine
A3 Swing posts (2) 90 x 90 x 3600mm Treated pine
B Cubby beams (3) 140 x 45 x 1500mm Treated pine
C Verandah beams (3) 140 x 45 x 2225mm Treated pine
D End beam 140 x 45 x 2400mm Treated pine
E Cross beam 140 x 45 x 1410mm Treated pine
F Short beam 140 x 45 x 990mm Treated pine
G1 Floor (long – 17) 90 x 22 x 2400mm Treated decking
G2 Floor (short – 9) 90 x 22 x 990mm Treated decking
H Wall plates (8) 70 x 35 x 1320mm Treated pine
I Wall studs (12) 70 x 35 x 1405mm Treated pine
J Window sill/head (2) 70 x 35 x 640mm Treated pine
K Window stiles (2) 70 x 35 x 350mm Treated pine
L Door heads (2) 70 x 35 x 575mm Treated pine
Item Part Size Material
M Top chords (4) 90 x 45 x 960mm Treated pine
N Bottom chords (2) 90 x 45 x 1510mm Treated pine
O King posts (2) 90 x 45 x 230mm Treated pine
P Battens (4) 70 x 35 x 1460mm Treated pine
Q Weatherboards (total) 140 x 19 x 75m Treated pine
R Roofing (4) 1110 x 890mm Ripple iron
S Capping 1500mm Galvanised steel
T Barge (4) 140 x 19 x 1030mm Treated pine
U Fascia (2) 140 x 19 x 1500mm Treated pine
V Lattice channel (total) 90 x 45mm x 12m Treated pine
W Lattice (2 panels) 2400 x 1200mm Treated pine
X1 Ladder rails (2) 70 x 45 x 1300mm Treated pine
X2 Ladder rails (4) 70 x 35 x 490mm Treated pine
Y Swing beam 90 x 90 x 1900mm Treated pine
Z Trim (total) 90 x 19 x 8m Treated pine
Check all measurements against project as you build. You will also need nine bags concrete mix; 14 x 120mm and 12 x
150mm by 10mm diam galvanised cuphead bolts, washers and nuts; three 150mm bridge spikes, six 45 x 90mm joist hangers,
galvanised spiral decking nails, assorted galvanised nail plates, swing and climbing rope with fittings, fibreglass slippery dip
and handles. Use only galvanised fixings.
Step 3 Bolt one of cubby beams
Step 9 Cut roofing (R) to leave a
Step 5 Nail wall plates (H) to
Step 10 Cut verandah posts to
Step 4 Before fitting decking, use
for trim (Z) around
door and window openings.
battens (P) to the trusses
70mm from top and bottom.
Step 14 Add slippery dip to side
Step 8 Cut V joint weatherboards
108303517.032.png 108303517.033.png
SHOPPING Cubby house developed
and built by Nikos Grammenos
(02) 4751 6190. All materials Johnson
Bros, Mitre 10 (02) 9999 2130.
Swings, handles, slippery dip Playcraft
(02) 9634 7249. Power tools Bosch.
BELOW
A Erect posts with perimeter beams, then check
that construction is level.
B Metal joist hangers hold intermediate beams at
same level as perimeter beams.
C Lay the top chords of truss over bottom chord to
mark cutting angle.
A
B
C
108303517.001.png 108303517.002.png 108303517.003.png 108303517.004.png 108303517.005.png 108303517.006.png 108303517.007.png 108303517.008.png 108303517.009.png 108303517.010.png 108303517.011.png 108303517.012.png 108303517.013.png 108303517.014.png 108303517.015.png 108303517.016.png 108303517.017.png 108303517.018.png 108303517.019.png 108303517.020.png 108303517.021.png 108303517.022.png 108303517.023.png 108303517.024.png 108303517.025.png 108303517.026.png 108303517.027.png 108303517.028.png 108303517.029.png