Carport - Free Standing, Flat Roof.pdf

(155 KB) Pobierz
Free-Standing Carport
Free-Standing Carport
PLANS AND INSTRUCTIONS
This is the Metric version
Free-standing flat roof carport.
This single carport is 6000mm long by 3000mm wide. It is the most basic of
carports. Because each site is different, and individual preferences vary, we have
given options for both post installation and bracing. Check with your Local Authority
to see if any permit or consent is required. A building consent for a carport is
required in New Zealand.
Identifying the members
(a) Posts 100x100
(b) Beams 200x50
(c) End rafters 200x50
(d) Rafters / Purlins 150x50
(e) Noggings 150x50
(f) Galvanised bolts
(g) Joist Hangers
(h) Galvanised Angle Bracket
The timber
The timber for this project can be either sawn (rough sawn) or dressed (gauged,
smooth finish). The measurements used in this project are for sawn timber. If
dressed timber is preferred, make allowances for the difference in timber thickness
and width.
Use a timber suitable for in-ground applications for the posts such as pressure
treated pine H4 or H5 and use a timber suitable for exterior applications for the rest
of the carport structure, such as pressure treated pine H3.
Any timber merchant or supplier will be able to advise on the timber most suitable.
The height
The height of a carport is in most cases, common sense. A tall person should be
able to walk comfortably under the lowest end of the carport. 2100mm from the
finished ground to the underside of the lowest end rafter, is a good height.
The slope
The roof slope (fall) should be at least 50mm. In this project the slope is 100mm. If
using a clear PVC roof, then a steeper slope is advisable, as a steeper fall (say
112933721.009.png 112933721.010.png 112933721.011.png
150mm) means faster water run-off, and therefore a cleaner roof.
The plans
The plans (click on the thumbnail) show a flat plan "bird's-eye view"
and an elevation (side) plan giving all dimensions. Refer to these
plans for any required measurements throughout the project.
Setting out
Mark out the carport (6000mmx3000mm rectangle) and erect timber profiles out
from each corner and also out from the middle to take in the two center posts. Set
the timber profiles back at least 600mm from the building line (carport perimeter) to
allow room for hole digging etc. For instructions on making timber profiles click here.
Attach stringlines to indicate the centres of the six posts 100mm in from the side
edges and 350mm from the front and back edges.
INSTALLING THE POSTS
Method 1. Post set in concrete.
Dig post holes 300mm square by 600mm deep. Place 100mm of
concrete into the bottom of every hole.
Commence putting the posts in the holes against (but not touching)
the stringline. Using a spirit-level on both the front and side faces,
check that the post is plumb (vertical) and almost, but not quite,
touching the stringline.
Fill the hole with concrete to within 50mm of the finished ground level.
Check again that the post is plumb and not quite touching the
stringline. Because of the depth of the hole, the concrete will support
the post without the need for bracing. Continue until all posts are
concreted in.
Method 2. Galvanised post brackets set in concrete.
Dig post holes 300mm square by 600mm deep. Fill the holes with concrete and set
the brackets in position while the concrete is still soft. Ensure the brackets are at the
right height, taking the finished slab (carport floor) into consideration. Some
temporary packing, props or bracing may be needed to support the brackets until
the concrete stiffens up. Wait until the concrete has cured (usually at least four
days) and then install the posts plumb (vertical) in the brackets and hold in place
with temporary bracing.
Method 3. Galvanised post brackets bolted to existing concrete slab.
Fix the brackets to the slab, in position with masonry bolts or anchors. Install the
posts plumb (vertical) in the brackets and hold in place with temporary bracing.
TRIMMING THE POSTS
Mark the rear posts a minimum of 2300mm above the slab, or finished ground level.
Ensure the height marks on both rear posts are level. Use a spirit-level on a straight
edge to achieve this or the water level method. Mark the front two posts 100mm
higher than the rear posts. Fix a stringline between the front and back posts to mark
the height of the middle posts. Cut the tops of the posts off at these marks.
THE BEAMS AND RAFTERS
112933721.012.png 112933721.001.png
Cut the two beams 6000mm long with 45degree angle cuts each end
and clamp in place to the posts so that the tops of the beams are
flush with the tops of the posts and protrude past both the front and
rear posts by 300mm. Drill and bolt the beams to the posts with M12
galvanised bolts, (two at each meeting).
Cut the two end rafters 3000mm long with 45degree angle cuts each end and fix in
place to the beams with 75mm jolthead galvanised nails and then with galvanised
angle brackets, each bracket fixed with four M12 galvanised bolts, two through the
beam and two through the rafter. (See diagram).
Cut the six intermediate rafters 2900mm long and fix in place to the beams with
galvanised metal joist hangers. Space the rafters at 900mm centres (crs, o.c.). See
Finish off with a longitudinal row of trimmers (noggings) down the middle and in
between the rafters.
THE BRACING
If the posts are concreted into the ground, and the posts are bolted to
the beams with two bolts at each meeting, then no further bracing
should be required. If, however, the posts are not in-ground, but
supported by galvanised post brackets, then additional bracing is
required. One such scenario is to fix upper post diagonal bracing (see
diagram) , two to each post, each about 900mm long (more or less),
and fixed to the post with nailplates and fixed to the beam/rafter with
bolts.
Another scenario is to fix full 100x100 diagonal braces running from the bottoms of
the middle posts to the tops of the end posts and secure with bolts, nail plates or
galvanised brackets at each end. A similar diagonal brace is also required between
the two rear (end) posts. With this latter scenario, the diagonal braces could be
replaced with diagonal trellis (lattice) between the two end posts and the end post
and middle post each side (three panels in all). Both bracing methods mentioned in
this scenario also require roof plane bracing to ensure the front of the carport is
rigid. This can be 25mmx1mm flat galvanised metal strapping stretched from corner
to corner and fixed with galvanised nails to the top of each rafter.
THE ROOF
You can now apply your chosen roof.
All done. Eazy with a "Z"!
Glossary of terms used in this project
BEAM: A supporting member.
BRACE: To make rigid
BUILDING LINE: The outline of a
building.
CENTRES: Crs; O.C; Term used for
spacing; The measurement of spacing
for studs, rafters, and joists in a
building from the center of one
member to the center of the next.
CRS: See centres.
JOLTHEAD: General purpose
nail. Small round head.
LONGITUDINAL: Running the
length of the building.
M12: 12mm thick galvanised
bolt.
MASONRY: Stone, brick,
concrete, hollow-tile, concrete
block, or other similar building
units or materials.
PROFILES: Timber profiles;
Horizontal boards attached level
to stakes, used to mark out the
boundary of a construction and
establish the levels.
PVC: Plastic type roof, spouting
and downpipe.
RAFTER: Parallell members of a
roof that support battens/purlins
and roofing materials.
112933721.002.png 112933721.003.png 112933721.004.png
CURE: Mature; Harden; Set.
DIMENSIONS: Any of the three linear
measurements, length, breadth, and
depth.
DRESSED: Relating to timber.
Planed; Smooth, even surface;
gauged.
ELEVATION: Side view of a building.
END RAFTER: Rafter each end of the
roof frame.
FALL: Of roof. Pitch; The incline angle
of a roof surface.
FLUSH: being even with
GALVANISED: Covered with a
protective coating of zinc.
GAUGED: See dressed
H3: Of timber Presure treated suitable
for exterior use but not in-ground.
H4: Of timber Presure treated suitable
for exterior use and in-ground
applications.
H5: Of timber Presure treated suitable
for exterior use and in-ground
structural applications.
JOIST HANGER: U shaped metal
hanger attached to a bearer or beam,
into which a joist or rafter is fitted.
MASONRY BOLT/ANCHOR:
Special screw or bolt for masonry
that expands when tightened.
MEETING: Where two members
meet.
MEMBER: Piece of timber that is
part of a frame or structure.
NAIL PLATE: Gang nail plate;
Metal plate with rows os sharp
points that are hammered into
butt-jointed timber to secure the
join.
NOGGING: Trimmer; A short
piece of timber set between two
studs, joists, rafters or purlins to
keep them rigid.
O.C.: On centre; (See centres)
PERIMETER: boundary.
PLANE BRACE: A diagonal
brace running along the plane of
a roof.
PLANED: See dressed.
PLUMB: Vertical; Upright.
PURLIN: Timber used to support
roofing sheets. Usually fixed on
top of rafters, but in this case the
purlins are the rafters.
RECTANGLE: Four sided figure
with four right angles.
ROOF PLANE BRACE: See
plane brace.
SAWN: Rough sawn; Not
gauged, planed or dressed.
SLAB: Of concrete; pavement,
i.e. driveways, garages, and
basement floors.
SLOPE: See fall.
SPIRIT LEVEL: Tool used to
ensure surfaces are level or
plumb by means of a bubble in a
tube of liquid fitted to the level.
STRINGLINE: A slightly elastic
string stretched between two
pegs and used as a guideline.
Determines the building line.
TIMBER PROFILE: See profiles.
TRIMMER: See noggings
VERTICAL: See plumb.
The Carport Plans
and Dimensions
The Carport Posts
112933721.005.png 112933721.006.png
The Carport Beams and Rafters
112933721.007.png 112933721.008.png
Zgłoś jeśli naruszono regulamin